Update on New Apparatus Order
 
By Collegeville FC Volunteers
March 13, 2023
 

The build process is under way for the new rescue engine with an anticipated late summer completion. Thank you to First Choice Fire Apparatus for the update.
This Apparatus was ordered on February 16th 2022 and will be delivered sometime in September 2023